New 20,000 square foot factory for Dartmeet Services Limited
December 2014

Installing 75 concrete piles

The column bases and foundation ready for concrete on the west side of the building

Trenches being dug and piles being cut down to take ground beams and pile caps

The first of the ground beams concreted

The first of the steel frame arrives from Ireland

Steel frame erection begins

Steel frame complete

Side cladding

Reinforcing ready for the concrete floor

The first pour of concrete in the floor - 180m cube

Concreting the floor